Title 17 LAND USE
Chapter 17.156 SITE SELECTION FOR ARTERIAL HIGHWAYS, INTERCHANGES AND COLLECTOR HIGHWAYS
17.156.020 Procedure.
Any "person" desiring to engage in the conduct of this activity
of State interest within Pueblo County shall file an application for a permit
with the County of Pueblo and its Land Use Administration. "Person," as defined
by statute, is any individual, partnership, corporation, association, company,
or other public or corporate body, including the federal government and includes
any political subdivision, agency, instrumentality, or corporation of the
State.
No later than thirty (30) days after receipt of application,
the County Land Use Administration will publish a notice of a hearing of the
permit application. Such notice shall be published not less than thirty (30)
days nor more than sixty (60) days prior to the date set for the hearing and
shall be given to the Colorado Land Use Commission.
The County of Pueblo may approve an application for permit to
conduct this activity of State interest if the proposed activity complies with
the County’s guidelines for the conduct of site selection of arterial
highways, interchanges and collector highways within the County of Pueblo. If
the proposed activity does not comply with these guidelines, the permit shall be
denied.
No later than forty-five (45) days after the hearing date,
the Board will either grant or deny the permit request.
A permit to conduct this activity shall be required at the
following time, respectively:
1. For major additions to the 1990 Thoroughfare Plan: prior to
submittal to the State.